CIBINONG PHASE III EXTENSION PROJECT
PROJECT LOCATION
Cibinong, West Java, Indonesia
PROJECT SUMMARY
6,000 MTPD Cement Plant
CUSTOMER
PT. Semen Cibinong
MAIN CONTRACTOR
Hyundai Eng. & Const. Co.,Ltd
WORKSCOPE
Steel Structure : 2,637 tons
Erection : 8,071 tons
Piping Fabrication and Installation : 426 tons
Maintenance and Commissioning
CONTRACT AMOUNT
US $ 6,700,000 (excluding additional work)
TIME FRAME
March 1990 – July 1992